What the source supports
- The approval covers solar generation, battery backup and associated distribution infrastructure.
- The reported contract value was approximately Tk 174.18 crore.
- Approval is not the same as completed construction or operational status.
The source confirms purchase-committee approval and the reported contract value. Final contract execution and project schedule require project documents.
The Cabinet Committee on Government Purchase approved a turnkey solar plant with battery backup and associated distribution infrastructure under a Power Division project.
The approved scope
The committee approved a turnkey package under the Bhasan Char electrification project, combining a solar plant, battery backup and distribution works.
Reported contractor
BSS reported that the contract had been awarded to a joint venture of Suhua Construction Group Co. Ltd. and Power System Development Co. Ltd.
Why storage matters
For an island or constrained network, battery storage can support supply continuity, ramp management and the use of daytime solar outside production hours. Actual capability depends on the specified MW, MWh, controls and operating strategy.
Verification still required
VOLTLENS requires the signed contract, technical capacity, delivery schedule, warranty, safety requirements and commissioning evidence for the project profile.
The source confirms purchase-committee approval and the reported contract value. Final contract execution and project schedule require project documents.